Progress report 1
1)
Select topic for the project based on the syllabus in the book- CD-ROM.
2)
Distribute task to all members
3)
Search the web hosting.
4)
Send the topic that selected to Mr. Uwe.
Progress report 2
Date: 15 July 2002
1)
Register the website in the web.
2)
Make the front page of the web site
3)
Discuss the contains of the website
4)
Search the information about the topic
5)
Send the URL to Mr. Uwe
6)
Make the progress report and built the Gannt Chart
Progress report 3
Date: 22 July 2002
Time:1.00 p.m. to 2.00 p.m.
Venue: Uniten Library
Activity: We
make a research together. Discuss about the contents and try to figure out the
idea to decorate the website, so that the website will more attractive and
interesting. Mohd Syazwan try to find out more pictures about the cd-rom and
Asfia translate back the sentences in his own word. Nur Hazwani try to search
information and translate it back by make a new sentences.
Date: 27 July - 3 August 2002
Activity:
Mohd Asfia:
Update website and search information
Mohd Syazwan:
Translate the texts and find out pictures
Nur Hazwani:
Arrange the contents of the website and complete the progress report
Progress report 3
Date: 4 - 13 August 2002
Activity:
Mohd Asfia:
Update the website but had involved in accident on 11 August
Mohd Syazwan:
Make a photocopy of information and scan pictures
Nur Hazwani:
Finished translate the information from the text book and update the website
Progress report 4
Date: 16 August 2002
Time: 11.00 a.m. to 2.00 p.m.
Venue: National Library, Kuala Lumpur
Activity:
Today we (except one of our member, Mohd Asfia who had involved in accident on
11 August) met again and our first objective is to make some research and find
more information for our project. Here we found a lot of info related to what
we are going to present. We decide to add more informative facts to our
contents and arrange back our data. The method that we use to get the
information is by photostat all the information from the books and translate
them in our own sentences. We distribute the tasks to all the members and each
of us have to complete translate it during the limited period.
Progress report 5
Date: 7 September 2002
Time: 11.30 a.m. to 12.30 p.m.
Venue: Uniten Library
Activity:
Today we discuss about on how we want to edit our information into our website.
We also discuss about the topic that we should edit start from now. Then we
list out all the topics that we had finished translated and give them to Asfia
to make final check out.
Progress report 6
Date: 27 September
2002
Time: 2.00 p.m. to
3.00 p.m.
Venue: COE café
Activity: We met
at COE café to make our last discussion about our project before we
submit them. We arrange back the data and try to complete
all the arrangement for the website. We also discuss if there any other topic
is not include We gathered all the materials to be edit by Asfia. We suggest to
put some graphics to our website. Then, we discuss what kind of graphics that
we want to use
Progress report 7
Date: 2 October 2002
Time: 11.00 a.m.
Venue: BL-3-016
Activity: This is
our last meet. We all together make the last touch up and arrange all the data
that will be publish on the website. We gathered all the information that we
have and put them according to the contents that we had decided before. Finally
we publish it in the website.
|